What is a submittal in construction, and what does approval actually mean?
A submittal is what the contractor sends for review before installing. The four types, and why "approved" does not mean accepted.

A submittal in construction is a document, drawing, product data sheet, or physical sample the contractor sends to the design team for review before the related work is fabricated, ordered, or installed. Its purpose is to confirm that what the contractor intends to provide matches what the contract documents require. For an owner running repeatable buildouts, this is the stage where the building you will operate for the next fifteen years is actually decided.
The four types of construction submittals
| Type | Prepared by | Reviewed for | Owner’s real interest |
|---|---|---|---|
| Shop drawings | Contractor or subcontractor | Conformance with the design concept | Whether it fits and coordinates with adjacent work |
| Product data | Manufacturer, forwarded by contractor | Whether the specified product is what is proposed | Substitutions, and what you will maintain |
| Samples | Contractor or supplier | Appearance and workmanship standard | Brand consistency across locations |
| Closeout submittals | Contractor and suppliers | Completeness | Warranty start dates, serial numbers, parts |
Who reviews a submittal, and in what order
- 01The subcontractor or supplier prepares the submittal and sends it to the general contractor
- 02The general contractor reviews it for coordination with adjacent trades, then transmits it
- 03The architect or engineer of record reviews it against the design concept and returns an action
- 04The owner reviews it where the specifications require owner review, typically for brand standards or equipment
- 05The action is recorded, and the work proceeds or the submittal is revised and resubmitted
What does an approved submittal actually mean?
Less than most owners think, and the contract documents are unambiguous about it. AIA A201-2017 states that the architect reviews submittals for the limited purpose of checking conformance with the design concept, not the accuracy and completeness of finite details; the contractor keeps responsibility for means, methods, and coordination. EJCDC C-700-2018 is blunter: submittals are not Contract Documents, and a review cannot serve as a change order. A stamp on a submittal does not transfer responsibility to the design team and does not amend your specification.
Where substitutions enter the process
Specifications commonly name a product followed by "or equal," permitting the contractor to propose an alternative meeting stated requirements. On a single project this is ordinary. On a program of forty stores, it is how your standard erodes: each site proposes a reasonable equivalent, nobody compares the substitution approved in one market against another, and four years later you operate a dozen rooftop unit models where the prototype named one, with no document anywhere that says so.
- Warranty terms and start dates change with the manufacturer
- Spare parts and service capability shift away from what your vendor stocks
- Physical fit changes dimensions, curb, and structural load, feeding stale as-built drawings
- Energy performance and rebate eligibility can be quietly disqualified
- Landlord consent granted for one unit is not consent for another
Frequently asked questions
What is the difference between a submittal and an RFI?
- A submittal proposes what the contractor intends to provide, for review against the contract documents. A request for information asks a question about ambiguous or missing requirements. A submittal returned as revise and resubmit frequently produces an RFI.
Is a submittal a contract document?
- No. EJCDC C-700-2018 states that submittals are not Contract Documents and cannot modify contractual requirements or serve as a change order, which is why an accepted substitution is on weaker footing than one processed as a change order.
How long does submittal review take?
- The specifications set the period. UFGS 01 33 00 allows 15 working days for QC manager approval and 20 for contracting officer approval on Navy projects, plus an additional 14 calendar days for variations, though private projects commonly specify shorter periods.
Who is responsible if an approved submittal turns out to be wrong?
- Generally the contractor. AIA A201-2017 limits the architect’s review to conformance with the design concept, leaving means, methods, and coordination with the contractor. The practical protection is a specification requiring deviations to be disclosed in writing.
See REAL run end to end.
Watch a demoRelated posts
Bid analysis measured against your own track record
How to price every line item on real delivery cost instead of the number a vendor hands you.
Estimating store buildouts on real delivery cost
A look at how disciplined estimating tightens budgets across a national rollout.
Best construction budgeting software for 2026
Construction budgeting software ranges from general contractor tools to capital-project governance to retail rollout platforms. Here is how four compare.